Click here to go to the website homepage
UK Site
Click here to view the Danish Esscano website
Danish Site
Tel: +44(0) 1778 560562
Home Products The Company Case Studies Contact Us Sitemap
  • Esscano Power improves tightness of competitor’s Double Louvre Damper
  • Lining with C22 Hastelloy saves money in corrosive gasses application
  • CIP (Clean-in-place) dampers with hygienic design for the food industry
  • Damper upgrade to minimise dust and heat loss through seals on competitors equipment
  • Esscano Inlet and outlet dampers used to prevent condensation in Textile Bag Filter
  • Steam Turbine installed as part of the L90 Waste Incinerator facility at Esbjerg, Denmark

  • Esscano Power improves tightness of competitor’s Double Louvre Damper
  • Lining with C22 Hastelloy saves money in corrosive gasses application
  • CIP (Clean-in-place) dampers with hygienic design for the food industry
  • Damper upgrade to minimise dust and heat loss through seals on competitors equipment
  • Esscano Inlet and outlet dampers used to prevent condensation in Textile Bag Filter
  • Steam Turbine installed as part of the L90 Waste Incinerator facility at Esbjerg, Denmark

Steam Turbine installed as part of the L90 Waste Incinerator facility at Esbjerg, Denmark

Esscano Power A/S and  B+V Industrietechnik GmbH secured the contract to supply the Steam Turbine Plant for the L90 Waste Incinerator facility at Esbjerg, Denmark.

This plant is owned by 35 municipal councils and is designed to burn 180.000 tons of waste per year. Approximately 90 tons of steam per hour is produced and feeds the B+V Steam Turbine at a pressure of 40 bar and at a temperature of 400 ˚C. At full load, this turbine will produce an output of 18.5 MW of power and deliver 51 MW of energy to the local district heating system.

Work started in the spring of 2002 with Esscano Power A/S representing B+V Industrietechnik GmbH’s interests on site, where we provided project coordination services with the Builder, Consulting Engineers and other contractors.
 
Esscano Power was responsible for the supervision of the erection and the work of B+V Industrietechnik’s sub-suppliers and subcontractors to ensure the work was done to specification.
 
Esscano Power A/S commissioned, tested and handed over the plant on time in mid 2003.

The Scope of Supply included:

• Complete turbine/generator plant incl. control panel
• Complete Bypass system incl. control panel
• Feed Water Tank
• District Heating Heaters
• Complete district heating system incl. Equalisation Tanks
• Water Treatment plant
• Complete 10kV plant
• Complete panel system incl. Main Distribution Panel for other contractors